Applemead House, Whimple Progress

December 2, 2019

At the start of week 25 in the contract, the System Six kitchens are being fitted, tiling the bathrooms, decorating throughout, rendering the outside and 2nd fix M&E are all works being carried out.

The external bat box will be going up over the next couple of weeks for our resident bat called Mike.

The photographer has been booked for taking the marketing photos on the show apartment before Christmas and the marketing will begin.