Applemead House, Whimple – Progress

November 8, 2019

At the end of week 21 in the contract, the velux windows have been installed, the natural slate roof is complete and the triple glazed windows have been fitted.

Internal works have pushed on, with the 1st fix M&E, insulating and boarding all complete.

Plastering internal commences Monday next week and the external rendering shortly after. Kitchens will start to be fitted by the end of November.

With the excitement gathering around the sales, with the end in clear site we are all looking forward to 2020.